2 Replies Latest reply on Nov 26, 2010 8:48 AM by 813340

    NEED BY DATE

    810902
      Hi Guyes,
      In oracle Sourcing when the buyers received the approved line(s) for any purchase requisition for the purpose of creating Sourcing RFQ, he will put the closing date of that RFQ before the need by date which came from the approved requisition line(s)
      My question is if the supplier does not submit the required quotation within the RFQ closed date or before as the RFQ predifines rules the buyer can manulay extend the closing date which also must by before the need by date but also the supplier does not submit his required quotation, in this case can the supplier assigned a new closing date beyond the need orginal need by date ?

      Regards

      Hazem Mahmoud