0 Replies Latest reply on Dec 21, 2010 8:03 PM by 802394

    Help with % complete

    802394
      I am having an issue using duration % complete. If an activity is completed and then no more activities are worked for some time, that activity holds more weight with each week that the schedule is scheduled foward. I can't have this, because it is giving to high of an overall % complete. Is there a way to show the overall percentage complete based solely on the work complete with out taking in the time that has elapsed? This is causing me to produce inaccurate production schedules, that doesn't show an accurate percentage of the work that has been done. Physical % complete doesn't show an overall % on the WBS level, and Performance complete only shows the activities that has a budget to them. My settings are Duration Type: Fixed Duration and Units/Time and % Complete Type: Duration. Thanks for any help.