1 Reply Latest reply on Feb 9, 2011 3:23 PM by Sandeep Gandhi, Consultant

    Blanket purchase Agrement

    835644
      Dear Experts

      I have Created Blanket purchase Agrement for a period of 1 year ... and i have one release with some quantity.... supplier has sended and now we need to put receipt...here suppose price of the item has decreased nearly 50% and now i need to change amount in agrement ...how i can do ?

      if we change agrement it need re approval right ? if it is re approved now what will happened with the quantity which is waiting for receipt?
      2)if suppose we received first release before changing the agrement...what will happens ( can we change price of the item before payment)?