      i'm loading a lot of data to different entities within HFM using the batch loader.

      I would like FDM to trigger a force calculate but nog a consolidate (since it takes very long).

      Can anyone please advise how to do that?

      Thanks in advance,

      Marc
        • 1. Re: FDM to HFM calculate instead of consolidate
          SH_INT
          In the integration settings make sure that you have the force calculate option enabled as well as the consolidation option. Then in your entity validation groups ensure that the consolidate checkbox is unchecked against all your entity definitions. Only a force calculate will then be performed on the entities defined in your group.