    How to Earn Value for a Level of Effort EV Type of Activity

    912143
      Is there a way in P6 to earn performance based on the Data Date so that the EV Labor Units and EV Labor Cost is equal to the Planned Value Labor Units/Cost?

      We have several "Level of Effort" type of activities (speaking in EV terms, not the Activity Type in P6) that should earn performance as time passes EXACTLY as the work was baselined. However, when the Data Date is updated the "Planned Value" data is updated correctly but the "Earned Value" fields are updated based on the duration % complete and does not take into account the spread of units over time.

      Since these are LOE activies there cannot be a schedule variance (Planned Value data needs to equal Earned Value data).