    running more than one batch on the same resource at the same time.

    907453
      Dear all,

      as i'm working in paper industry , i have to release more than one batch at the same time using batchable resource , but i have problem in declaring the resource usage , if i run 3 batches on the same resource for i hour , what is the resource usage for each batch and how the system will help me to know that.


      Regards.
        • 1. Re: running more than one batch on the same resource at the same time.
          user355059 raj_ntt data india
          Hi

          My question is If I run 3 batches on the same resoures......what do you mean

          Assume you have 3 batches names b001/boo2/boo3

          for B001 you have planned resoues as 1, but Actual resouce count is 2
          for B002 you have planned resourse as 3 but Actual resource count is 3
          for B003 you have planned resourse as 2 but actual resouree count is 2

          Here the the Acutal resource usage will calculate as per the actual count and that too within Batch only. And it will not consolidte Batches altogehter.

          Rgds
          Raj