    Milestones: Max Start falling after Max Finish??

      I am a recent user of PRA and in putting a schedule through a thousand iterations most of the dates came out perfectly fine but after being asked by a project manager to look at 3 milestones, after looking at the duration probabilities of the 3, the first (near the start of the project) had a perfectly normal max finish falling one day after the max start, but the other 2 (at the latter end of the project) were showing that the max start finished a day after the max finish.

      Does anyone have an idea as to why this is happening and the reasons behind it?

      Any help anyone could offer would be greatly appreciated,