    How to solve negative float in P6?

      I baselined a schedule that has around 1,100 activities a couple of months ago and I'm updating it on a bi-weekly basis. When I issued the baseline, my float was zero, in other words, I didn't have negative float. Now, I'm getting big negative floats, especially on ongoing activities that have a 7-day calendar. Why? Can anybody help me on this matter? Thanks in advance.