wrong distrubution of resources

930079 Newbie
Currently Being Moderated
Hi there,

I have a problem with my resource distribution in P6. the problem is that resource distribution (budgeted labour unit) doesn't fall within the same range of related activity's start and finish. For example, activity itself started at 21.Nov.12 and finished at 28.Nov.12 but its resources is showing from 03.Apr.12 till 10.Apr.12.
I would be very thankful if anyone has any idea about that.

Thanks in advance,
Raja