1 Reply Latest reply on Apr 17, 2012 10:27 AM by Paarthy-Oracle

    integrate project with supply chain`

    927217
      Hello
      From projects, is it possible to import material requirment to purchase requisition, if yes, kindly advise process as well.
      thanks
      S
        • 1. Re: integrate project with supply chain`
          Paarthy-Oracle
          it should be possible from project deliverables

          steps:

          1) Assign a deliverable for the tasks
          2) Create an action
          3) complete all the information (destination type is EXPENSE)
          4) click on Ready to Procure
          4) save and apply
          5) publish the Workplan
          6) click on Initiate Procure in the Deliverable
          7) Run Requisition Import

          Project Deliverables FAQ (Doc ID 834194.1)

          Is Project Contracts (OKE) required to use Deliverables in Project Management?

          You do not need to implement Oracle Project Contracts (OKE) to integrate project deliverables with Manufacturing Planning and Shipping. If you do not have OKE installed, you will need to apply Patch 4252634 ‘Oracle Project Contract (OKE) functionality for Oracle Projects Family Pack M (Deliverable)’. See Note 375283.1 for details. Also noted in the PA.M ‘About’ document.

          it is actually a question for projects forum, please post it there!