    updating baselines

    1983-PLANNER
      Sir,

      This is regarding updating projects with baseline.
      Suppose i have a project P with baseline B1. Now i add 2 new activities to the project such that the new activities appear in both baseline B1 and actual updating project (with same start and finish date)Ho to do this??


      Please advise..

      Thanks,
      Imad
        • 1. Re: updating baselines
          924630
          Hi Imad,

          Project -> Maintain Baselines -> (select Baseline Project) -> Update Baseline (button). Then uncheck every box except 'Add new activities and activity data (except actuals)'. I think this will accomplish what you want to do. Of course, you could also restore the baseline, add the activities and add it again as the baseline.