3 Replies Latest reply: Sep 10, 2012 10:11 AM by Hussein Sawwan-Oracle RSS

    Upgrading Discoverer from 10g to 11g

    balaji 762
      Hi

      We are on EBS 11.5.10.2 and also using Discoverer 10g from reporting from EBS.

      We have a plan to migrate EBS to 12.1.3 and Disoverer to 11g. What is the best option from the below ?

      Option 1: Upgrade to R12.1.3 and simultaneously do a fresh install of 11g and copy the EUL from 10g

      Option 2 : Upgrade the Disoverer to 11g by installing 11g and copying EUL from 10g - I believe this is possible only if you have ATG 7 running in 11i instance.

      Option 3 : Any other option

      Please suggest which is the best way to get to 11g discoverer

      regards,
        • 1. Re: Upgrading Discoverer from 10g to 11g
          Hussein Sawwan-Oracle
          We have a plan to migrate EBS to 12.1.3 and Disoverer to 11g. What is the best option from the below ?

          Option 1: Upgrade to R12.1.3 and simultaneously do a fresh install of 11g and copy the EUL from 10g

          Option 2 : Upgrade the Disoverer to 11g by installing 11g and copying EUL from 10g - I believe this is possible only if you have ATG 7 running in 11i instance.
          You can go with option 1 or option 2.

          You can either upgrade 11i to R12 then upgrade discoverer to 11g -- Using Discoverer 11.1.1 with Oracle E-Business Suite Release 12 [ID 1074326.1]

          Or, upgrade discoverer to 11g while you are on 11i then upgrade to R12 -- Using Discoverer 11.1.1 with Oracle E-Business Suite Release 11i [ID 1073963.1]

          Thanks,
          Hussein
          • 2. Re: Upgrading Discoverer from 10g to 11g
            balaji 762
            Dear Hussein,

            Which is the better option ?

            Wat are the pros or cons of either option ? thanks
            • 3. Re: Upgrading Discoverer from 10g to 11g
              Hussein Sawwan-Oracle
              Which is the better option ?

              Wat are the pros or cons of either option ? thanks
              If you want to eliminate the downtime of R12 upgrade, then upgrade Discoverer to 11g and make sure it is working properly with your 11i instance then upgrade to R12.

              Thanks,
              Hussein