    REDUCE THE ACTIVITY DURATION (P6 7.0)

    965297
      Hello Guys

      As simple as this question may seem I’m new to Primavera P6.

      I’m trying to add resources to an activity, to reduce the activity duration. For example, it takes 1 man 10 days to build a wall, however if I add another man to the activity (2 men) it would take only 5 days to build the wall.

      The problem I’m incurring is that my activity duration is not reducing. I guess it a setting that needs to be changed, so could you kindly please advise where I’m going wrong.

      Thank you