    Actual Cost Wrong

    971257
      Hi

      When i update my plan, by inserting the Actual Start & the Duration % complete, the P6 v8.1 calculates my Actual Cost wrong and also the At completion Cost too, but the remaining cost is right, this is happening while the activity in progress, but when the activity is completed everything goes OK.

      Any suggestions why this is happening, is there an option should i check it, by the way i checked the calculation tab in the Project menu, and also resources calculation tab in the WBS menu

      best regards,,

      Haitham