Project Performance Rules

936996 Newbie
Currently Being Moderated
Hello All

Is there a way that we can configure performance Rule and attach it for a Particular task on a Project instead of attaching it to a Project. For example if there are three tasks on a Project Say A, B, C . I want to configure a Performance Rule which will display' on Track' if Raw Cost reaches 30% of the Budgeted Cost for Task A, and Criticalif for Task B and nothing(No message or status indicator) for Task C.


Regards,
DR

Legend

  • Correct Answers - 10 points
  • Helpful Answers - 5 points