Hi ,

We have a requirement where we want a discrete job to reserve materials only from those LPN where there is no prior allocation.
for example:
Discrete Job1 requires 8 quantities of component A.
LPN001 has 10 quantity of item A.
Job1 should reserve 8 quantity of item from LPN001. Subsequently no reservation should be allowed for 2 available quantity of item A from LPN001 till the discrete Job1 is completed.