    Calendar change 8h/d to 7h/d

    981057
      Hello,
      When I have an action (calendar 8h/d) and I assigne a resource (calendar 8h/d) I will find for 150 m² planned units and 12,5 m²/h a duration of 12h.
      when I change the calendar of the resource in 7h/d I will find for the duration 13h.
      Why? Shouln't I find 12h as well, the units/periode and the planned units didn't change. Normally the duration only should change when I display durations in days.
      Is it because of the differents calendars assigned to the action and the resource? so do I always have to change the worked hours/day for the ressource and the action calendar?

      Thanks for your help
      Lena