1 Reply Latest reply: Dec 26, 2012 12:45 AM by 973217 RSS

    Problem during importing P6 file

    981346
      Hello,

      I am Importing P6 file in a P6 v6.2 and on P6 v7. After Importing I realize that the original duration is 0 or 1 !!!!

      I do scheduling, the start and finish date are fine as per the real imported project, but the original duration is still 0 or 1 !!

      Can you advise please

      Regards,
        • 1. Re: Problem during importing P6 file
          973217
          Hi,

          It is probably happening because of a conflict in calenders. Verify whether your project calender is same as the default calender.

          If not, then make the necessary changes and check for the durations again. You may also check for the appropriate original duartions column in the activity table.

          regards,
          Prasanna Babli