    Attachments to pull through activty steps


      I set an activity template with IN PLACE EDITING ACTIVITY TYPE.

      I create a new activity in a project by retrieving it from this activity template.

      I upload an attahchment in activity step 1.
      I move the activity on to step 2.

      I click on "ADD/NEW EDIT" button in the SUMMARY TAB.

      System gives me the possibility of pulling the attachment from previous step by thicking a specific field.

      However, if owner forgets to do it, owner in step 3 won't be able to pull it through anymore.

      Is there any way to make this tick automatic with the possibility of manually unflagging it when it is not necessary to pull any attachmet through?