    Scheduling alternative date sets

    991729
      Wouldn't it be nice if instead of automatically selecting the early start and finish dates on hitting F9/scheduling, you could pick from other date fields to chose which plan you'd like to see. For the purposes of creating a 3 point schedule for confidence modelling a schedule, I have entered dates for 'Best Case', 'Most likely' and 'Worst Case' into user defined text fields. It would be incredibly useful to schedule against these sets one by one to see the outcome. I don't want to have to create a copy of the whole date and call each one a What If. I'd like it all available from one plan at my fingertips.

      Anyone know of a way of doing this using currently available versions of Primavera?

      Anyone at Oracle care to include it in 8.3? It can't be that hard.