    Min Max Vs Reorder Planning

    user294688
      Hi All,

      What is the difference between both, Min Max & ReOrder Planning?

      Thanks
        • 1. Re: Min Max Vs Reorder Planning
          User315731
          Hi,
          Min-Max planning will be either maintained at Subinventory level or Organization level.
          If the onhand Qty falls below either minimum or Maximum level then system will generate either Purchase Requisitions or Work Orders in WIP module to replinish the inventory.
          On running the Min-Max report system will consider the existing Onhand,PO qty or the Sales Order demand as per the input parametres.

          Reorder Point is an alternate planning method for Min-Max planning method.
          This will replinish once the Item Onhand falls below {Safety Stock+(LeadtimeX Demand)}.This will also produce Purhcase Requisitions for replinishments.

          Thanks
          -Arif.