This discussion is archived
8 Replies Latest reply: Jun 14, 2013 2:44 AM by 1013031 RSS

Star mark on start or finish date without assigning primary constraint

1013031 Newbie
Currently Being Moderated
I am working on 4 project consists of almost 225 thousands of activities on Primavera p6v7. All four EPC and procurement projects are interlinked with each other. I am getting star mark (*) on start or finish date without assigning any primary constraints. Those activities are logically follow constraints too which gives non relevant dates and negative float. I can't import excel sheet too make any change to my projects, it shows out of memory.Can someone confirm how many activities Primavera supports? There is no filter at WBS level, I require to put filter at WBS level so that I could see only those activities which are under those WBS. The UDF's I defined at WBS level also not shown at Activity level, how to make WBS UDF's global? I want to paste the print screen on this forum but unable.....

Legend

  • Correct Answers - 10 points
  • Helpful Answers - 5 points