    how ı can shift activity's  start to the start of working hour of the next day ?

    user9166529
      what is the way to shift activity's  start to the start of working hour of the next day ?
      let me explain :
      A1000   :  Calendar 2 : ( work starts at 08:00 and finishes at 17:00 and 5 day/w )  : duration is 1 day
      A2000  :  calendar 1 : ( work starts at 09:00 and finishes at 18:00  and 6 day/w)  : duration is 1 day
      calendar for scheduling activity relationship lag : "successor activity calendar"
      when A1000 is linked to A2000 as FS , A2000 starts  in the same day after 17:00 when A1000 finishes . but I want it to start on the beginning of next day's first working hour.
      I cannot change schedule option to predecessor activity calendar because in that case ;  if A1000 finished on the 5 th day of week , A2000 start would shift to the beginning of next week .
      how could it be possible to arrange this?

       

       