0 Replies Latest reply: Nov 20, 2013 12:40 AM by User518167-OC RSS

    Actual Cost are not getting updating after assigning resource curve

    User518167-OC

      Hai all

          

      As I don't want the cost to be spread Linear , I assigned resource curve to all my assigned Resource .

      While updating the activities I have following issue .when the activity status is in Progress

          1.Actual Cost is not getting updated.
          2.Actual Unit is not Getting Updated.

      1. 3.Unit % Complete is not getting updated.
      2. 4.Earned Value is showing irrelevant Data.
      3. 5.At Completion Cost is not equal to budgeted total cost
      4. 6.At Completion unit is showing Irrerelevant data

                    

      In my Project Setting - Calculation Tab

       

          Link Budget & At completion for non started activity is ticked

          Recalculate Actual unit & Cost when Duration % Complete Changes is also ticked

      In Resource setting

            

      Auto Compute actual - Ticked

       

      Calculate Cost from unit is ticked

          

      Activity Type - Task Dependent

       

      Percentage Complete - Duration

       

      Duration Type - Fixed duration and units

       

      Presently I am manually updating the Actual Unit (Based on Duration% Curve value ) & At completion unit .
          

      All the above issue are solved when the above activity status is completed

      if the resource curve are removed from assignment all the

      above issue are solved.

          

      As of my understanding When we assign resource Curve
      Primavera will not automatically calculate & update the actual units
      or  Units % complete based on
      assigned  Resource curve value & we
      need to manually calculate based on Resource curve & to update the unit %
      Complete

       

      Is it Correct . If Not can anyone say how to fix the issue.