    P17714 Actual Labor

    OPalacios

      Hello, I´m working with Preventive Maintenance and I wish to know if there is a way to update the Actual Labor (LBAM) field from P17714 program (Accounting tab). I tried using the work time entry program P311221 and then running R13800 batch process.

       

      Any idea or suggestions?

       

      Regards

        • 1. Re: P17714 Actual Labor
          Rinami

          The time entry program you're using is Hours and Quanties which is used in manufacturing.  For CAM/SWM work orders you need to be using one of the programs for employee time entry.  The R13800 gets it labour actual hours data from the employee transaction history table (F0618) and combines that with the employee rates to get actual labour cost.  It will ignore any entries in the F31122.