    P6 to DispatchLogix to Collect EVM

    11cb483e-e863-4669-9859-cb9fc4482dc6

      Hello,

       

      We are collecting field progress with Dispatchlogix and now moving to update % complete with P6.   We have the field data updates and % complete updates into P6, now looking for updates from P6 into Dispatchlogix.  Has anyone done this before?  and what data points did you use back to Dispatchlogix.  We are likely never going to resource load the collection from P6 since Dispatch has the resources, man hours, equip, etc.   But any other touchpoint ideas that others have done would be great.  ref:  http://www.dispatchlogix.com/  to the API info. 