4 Replies Latest reply: Jul 23, 2014 3:28 PM by 906725 RSS

    Migrate the Planning Work Flow process from 11.1.1.3 to 11.1.2.3

    906725

      Gurus,

      We have upgraded our Hyperion Environment from 11.1.1.3 to 11.1.2.3. Could you please let us know the process or if there is a utility to migrate the Workflow process (Planning unit hierarchies) from the old Env?

      Currently when we go to Tools->Manage Approvals from the new version 11.1.2.3, its empty. The approach we used for the Migration was, exported the .ads from the old version, modified to 11.1.2.3 format, imported and deployed, post which we moved all the artifacts manually.