0 Replies Latest reply: Aug 1, 2014 7:11 AM by Duy Huynh RSS

    Budgeted Units Baseline Update BUG P6 v8.3.2

    Duy Huynh

      Dear all,

       

      When I am updating baseline for my project (add new activities), resource assignment Budgeted Unit (Labor) does not added to baseline correctly (Unit: 517, Duration 1), P6 set BL Budgeted Labor Unit equal to Duration which is 1, while expected should be 517. Is there any fix on this?

       

      Thanks & Regards,

      Duy