2 Replies Latest reply: Aug 6, 2014 10:33 AM by 2708621 RSS

    Can't view balances in Project Status Inquiry form




      I've loaded Project Budget values ( Approved Cost Budget) using an API and I can see that when I query it in the Budget form ( Projects Responsibility > Budgets), it is in submitted status. However when I query the project in Project Status Inquiry form, I expected to see some values in the field 'ITD-CST Bgt field, however, the value in the field is '0'. Do I have to set a profile option or does some other setup needs to carried out?