2 Replies Latest reply on Nov 3, 2014 6:12 PM by 2780142

    Scheduled Receipt dates in ASCP for POs are not correct

    2780142

      Has anyone else seen this behavior:  Our ERP has a PO delivery date of 12/1/14 and we confirmed this is also the date passed from our ERP to ASCP (both Need_By_Date & Promised_Date are set to the PO delivery date from our ERP).  However, following collections and a plan run in ASCP, the New_Schedule_Date in ASCP is 10/20/14...and we have no reference for where this 10/20/14 date is coming from.  This is causing the PAB and POH calculation to be incorrect.  Thanks.