2 Replies Latest reply on Feb 6, 2015 11:20 AM by Fabiano_r

    Sourcing - promised date

    Fabiano_r

      The supplier to populate the quotation in sourcing, the promised date is automatically populated with the date of need, it is possible to disable this option and show the field blank to force the supplier to populate.

       

      Appreciate any help

       

      Thanks!

        • 1. Re: Sourcing - promised date
          Abhi83

          There is no configuration/ setup which allows you to disable it. Your best shot is a customization.

          Also, if the delivery dates need to be captured it can be defined as a requirement and scoring can be done it based on number of weeks it would take a vendor to deliver.

          I used this approach for one of my projects.

          1 person found this helpful
          • 2. Re: Sourcing - promised date
            Fabiano_r

            I will customize, the problem is when SDC has over 100 lines, the supplier does not check all, it undermines the receiving process.

            Thanks for your answer.