3 Replies Latest reply on Jun 17, 2015 4:26 PM by robin.burgess12

    Running rapidclone on multiple apps tiers in parallel

    robin.burgess12

      Hi,

       

      I am working on a project to add 4 new apps tier nodes to our 12.1.3 RAC EBS environment. Currently, adcfgclone.pl is taking ~20 minutes to complete on each node, which is pushing our downtime out longer than we would like. Is it possible to run adcfgclone on each apps tier node in parallel, or should it be done one at a time? I know that it will be updating DB tables, so this may introduce some locking risk, but I'm not sure if the utility would be able to deal with it.

       

      Thanks in advance!

      Robin