    Release from Planner's workbench auto-triggers PO line Cancellation, how to restrict?

    user1128937

      Hi All,

      We have a requirement from business that, When a Purchase order is rescheduled in ASCP planner workbench, it sends recommendations for PO line need by date modifications and PO line cancellation and in EBS side PO lines are getting cancelled straight away. We would like to put a control on this point and as per the requirement buyer should be notified about line cancellation and they should take decision which lines to be cancelled. Can you please suggest a way to achieve this ?