0 Replies Latest reply on Jan 8, 2017 10:57 AM by Aykut

    MS Project (MPP) file

    Aykut

      Hi,

       

      I am using mpxj to read MS Project Files (mpp)

       

      Example 1:

      I have a Task a with given start date, but empty finish date.

      If I use mpxj, I do get for Finish Date the same value as Start date.

       

      Example 2:

      I have a Task a with empty start date, and given finish date.

      If I use mpxj, I do get for Start Date the same value as Finish date.

       

      TaskStartFinish
      Collect URsJanuary 1 207
      Approve URsFebruary 20 207

       

      I am simply using following code snippet:

      System.out.println(i + "\t" + task.getName() +  "\t" + " [ start ] "+task.getStart() +  "\t" + "[ finish ] "+task.getFinish());

       

      Does anyone knows the issue and how to workaround it?

      Any idea for another free mpp api other than mpxj ?

       

      Thanks, Aykut