      Hi All,

       

      We have a requirement in Integration project that Legasy system will send requisition details to Oracle E-Business suite system,Purchasing, and then we have to create purchase requisition with INCOMPLETE status. After that requisition will be submitted for internal  approval and in between, before the PR approved, Legasy system will send the updated requisition details to Oracle E-Business suite and we have to allow those update details and update the PR accordingly.

       

      We have found a note: 1916690.1 that <Moderator Edit - deleted contents of MOS Doc>

       

      Our issue is, if the requisition is in under going approval with status  'In Process', how to reset it to 'In complete'?

       

      Thanks,

      Pullareddy

       