    Importing an XER file tinto a P6 Database

    John854471

      When i get several xer schedules from a client to import into my P6 database (different project id #'s), should I change the action to "Insert New" for everything in the Modify Import Configuration), or just use the default as shown below.  My main concern is that a calendar or activity code will change between schedules if I keep the default action. My assumption is that it will not. My understanding is that only changes will occur if the imported P6 schedule has the same exact project id # as an existing schedule.