    Using a mix of steps and manual physical % complete in the same project


      I am working on a schedule that is intended to use both steps and manual entries as physical % complete to determine activity percent complete.  In the project view, the settings are checked as "activity % complete based on steps".  However, this has locked the physical % complete field from manual entry.  Any ideas for a workaround?  thanks