1 Reply Latest reply on May 31, 2018 5:09 PM by J Reinhart

    Purpose of PROJECT_ACCOUNTING_CONTEXT

    madhusudhanan

      Hello,

       

      We are trying to import PO with project reference and requisition.  On requisition distribution we have project details however project_accounting_context column is null.  While import do we need to populate project_accounting_context as Y?  What is the significance of the flag to set Y?

       

       

      regards

      Madhu

        • 1. Re: Purpose of PROJECT_ACCOUNTING_CONTEXT
          J Reinhart

          Hi Madhu,

           

          If you set project_accounting_context to Y/Yes, Oracle will verify that the required project information is populated.  It will require project_id and task_id in all cases, and if expense, it will require expenditure_type / expenditure_org_id as well.  If any required field is missing, you will get error POREQ-20110.  You may want to start setting the flag to Y, just as an extra check that the project columns are populated.  If you leave project_accounting_context null, it will still allow you to populate the project fields.

           

          If this answers the question, please mark it correct so that the question changes from unanswered to answered.

           

          Regards,

           