    ST/OT - Commitment to Quantity 1 (for ST) not creating OT

    3737402

      Hi,

       

      Trying to setup our ST/OT process so the ST commits to the Quanitity 1 (based on P4210 Processing options, Commitment Tab). However when we do this and create an ST it will not create the OT. If i turn this flag off (back to system default commitments) it works perfectly.

       

      Tried looking for a Bug/Fix but did not find anything - has anyones else found this issue.

       

      We are running E9.20

       