I haven't verified this with help in P6, but I believe allocation limit is from high-level resource planning. Are you assigning resources to the project or WBS elements? If yes, then you should see the allocation limit. If you are assigning resources to activities then you are not using the allocation functionality in P6 and the allocation limit line will not be displayed.
Did you show the limit line and uncheck the box for allocation limit?