      Do I need to consider Request_date as Last Run of the concurrent program from the table fnd_concurrent_requests?

       

      I can see other date fields as well: Please share your thoughts for considering Last Run date of the concurrent program.

       

       

      ACTUAL_START_DATEDATEThe actual time and date when the request started running
      ACTUAL_COMPLETION_DATEDATEThe time and date when the request was completed

       

       

      REQUEST_DATEDATEYesConcurrent request submission date

       

       

       

       

      Thank you in advance. Have a nice day :-)

        • 1. Re: Last Run Date of Concurrent Program
          John_K

          Request date = the date the request was scheduled to run.

          Actual start date = the date the request actually started running - will be different to the above, due to the manager wait times, work schedules etc.

          Actual completion date = the date the request completed.

           

           

          so if you want to know "when did the request last run?" - use actual start date.