0 Replies Latest reply on Dec 5, 2019 7:07 PM by 3399979

    Rapid Plan is NOT considering Processing LT from ASL

    3399979

      For our MRP buy item: We have setup Global ASL, Sourcing rule assignment to only one supplier.

      Processing Lead Time is setup in ASL.

      We see Processing LT from ASL in the collection workbench so it is collected in the VCP instance.

       

      Problem statement: Rapid Plan is NOT considering Processing Lead Time setup in ASL.

      On planner's workbench, when we see planned order, it is offset using processing LT of org item.

      When we use cross tab for Item, it shows processing LT from org item.

       

       

      What setup is missing?