      Hi All,

       

      We have an oracle 11.2 on redhat and  have  golden gate ddl replication at schema level between source and target.

      We are going to add new column in the existing table and sequences in primary.Please anyone share the below steps are fine.

       

      1,stop extract

      2,stop pump

      3,stop replicat

      4,add new column in  source

      5,add new column in  target

      6,add sequences in source

      7,add sequences in target

      8,start extract

      9,start pump

      10,start replicat

       

       

      Any suggestions.

       