    <p>I am attempting to setup our dev to match our prod essbaseenvironment. Using EAS, I would like to copy/migrate an theexisting database (*.otl, *.rul, *.csc files) from the productionenvironment to the development environment. Is there a way to"refresh" the Planning database in development with thenew database outline information that I copied from production?</p><p> </p><p>Simply put, it would be a similar process where using HyperionDesktop (Planning) to refresh/create the application from Planningdb to the Essbase db, but a backwards process instead. Does thatmake sense? Thanks.</p><p> </p><p> </p>
      • 1. Planning 4.0.1 - copy/migrate db via EAS 7.1.3
        3004
        <p>Hi,</p><p> </p><p>Copy the Production Planning schema to Dev along with Essbaseoutline and do the Incremental Database refresh . Then bothwill be in sync. Export production data and do import in Dev</p><p> </p><p>Hope this works...</p><p> </p><p>Thanks!</p>