    Lines are created multiple while changing requisitions via I-Procurement

    618177
      Dear All,

      If I want to change a requisition on the Requisition Status screen it is populated a few lines with the original line. (mostly it becomes 4 lines).

      It is only on the screen, not in the database until is checked out again.

      Any idea?

      Thanks and regards,
        • 1. Re: Lines are created multiple while changing requisitions via I-Procurement
          618177
          Finally, I found the root-cause of this issue. It is a complete bug of Oracle related to view "por_lines_v".
          Oracle view has a connection to oe_order_headers ooh where prh.segment1 = ooh.orig_sys_document_ref(+).

          It means that number of rows are populated to I-Procurement page is related to number of orders which has the same value for order reference for sales orders.

          Currently requsition numbers are around 25000. But there are some orders (Internal orders, so reference numbers were populated by Oracle, not from customer) has the same numbers.