    MRP Scheduling and how it relates to Lead Times

    707769
      Does Oracle consider all Lead Time values when running MRP?

      E.g. Pre-processing = 5 days (work days = 7 calendar), Processing = 50 days (calendar days), Post Processing = 20 days (work days = 28 calendar days)

      Will MRP consider all 3 variables when running MRP? E.g. will it look at the forecast requirement and count back a total of 85 days to come up with the date to release a PO?

      Thanks,
      BG