Incorrect WIP Job completion date

user562851 Newbie
Currently Being Moderated
Hi,

I need a help in understanding why weekends are included in WIP job completion date calculation logic.

e.g.: Item A has cumulative manufacturing LT as 4 days.

I created a discrete job manually with start date as today, up on save wip job completion date calculated as 9/6 which 4 days from now including weekends.

Our Org calendar has weekends off, but don't know why it considering Saturday & Sunday?

Thanks in advance.

- Sudhakar