Supply Planning Cloud
Discussion List
-
lead times not honored for reschedule suggestion?Summary: Hi Guru, will system honor lead time for rescheduling PO? i have an item with total lead time for 108 days, but when system is not honoring the LT when it comes…JasonZZZL 4 views 1 comment 0 points Most recent by Scott Malcolm-Oracle Supply Chain Planning and Collaboration -
Unable to enable the 'Enforce Capacity Constraints' in the supply planSummary: We require to enable the resource constraints on the Supply Plan, inpite of all the option been enabled at the offering level for the supply chain planning. Sti…Krupesh Joshi 15 views 3 comments 0 points Most recent by Krupesh Joshi Supply Chain Planning and Collaboration -
Is it possible to prevent it from release without maintaining the "supplier"?Summary: Content (please ensure you mask any confidential information): Version (include the version you are using, if applicable): Code Snippet (add any code snippets t…Supriya Singh 4 views 0 comments 0 points Started by Supriya Singh Supply Chain Planning and Collaboration -
Is it possible to automatically populate the supplier from sourcing rule during the release?Summary: Content (please ensure you mask any confidential information): Version (include the version you are using, if applicable): Code Snippet (add any code snippets t…Supriya Singh 4 views 0 comments 0 points Started by Supriya Singh Supply Chain Planning and Collaboration -
Supply Availablity not working for ATO item on redwood page.Summary: Summary: I was checking Supply Availability for ATO item on redwood page. Report is not getting generated. It is working fine for Components Items.ATO item supp…Saurabh Dubey-273423 12 views 2 comments 0 points Most recent by Saurabh Dubey-273423 Supply Chain Planning and Collaboration -
how required lead time and available lead time is calculated?Summary: Hi Guru, could you please enlighten me how this required lead time and available lead time is calculated? i have this item lead time set as 105 days but it's no… -
Can I delete a planned order in Supply PlanningSummary: In Supply Plan, Supplies and Demand table, user can manually create a planned order. Is there an option for user to delete/remove a planned order once it's crea…KKZ 46 views 5 comments 0 points Most recent by Gururaman Subramanian-Oracle Supply Chain Planning and Collaboration -
Redwood: Manage Planning Level Profiles Using a New User ExperienceRedwood: Manage Planning Level Profiles Using a New User Experience This redwood feature is only available in Demand Plan and not available in Demand and Supply Plan. In…Salman_Kotwal-Oracle 20 views 4 comments 0 points Most recent by Salman_Kotwal-Oracle Supply Chain Planning and Collaboration -
is there a list of backlog management error texts and how to trouble shoot them?Summary: I can see error texts like "Request Date out of range" but i don't know where that range is defined in backlog management. there are multiple other messages whe…felipe vieira 5 views 0 comments 0 points Started by felipe vieira Supply Chain Planning and Collaboration -
How to restrict users to run only specific plans (ex: Allow to Run Plan2 but not allow to run Plan1)Summary: we have Plan1 (Main plan), and Plan2(Simualtion Plan). we want to give plan run access for Plan2(simulation) , and restrict plan run access for Plan1. How can t…MD MERAJUDDIN 16 views 2 comments 0 points Most recent by Anushika Singh-Oracle Supply Chain Planning and Collaboration -
Custom Adjusted maximum quantity expression throwing an error" You can't view this table or graph.."Summary: I have a requirement to get adjusted maximum quantity by custom calculation. Custom expression is throwing an error in viewing replenishment policy parameter an…Badal.Soni 8 views 0 comments 0 points Started by Badal.Soni Supply Chain Planning and Collaboration -
Can we ensure that substitute items are considered during supply planning?Summary: Hi , The Item Structure defines a substitute item for a particular child item. Can we ensure that substitute items are considered during supply planning (uncont…eunjeong.kim 84 views 18 comments 0 points Most recent by Sebastian Thomas Supply Chain Planning and Collaboration -
Does Backlog Management Support Transfer Order Reprioritization?Summary: The Backlog Management module is primarily used to reprioritize and reschedule sales orders. Can it also be used to reprioritize or reschedule transfer orders? …Ketan Patil - Trinamix 18 views 2 comments 0 points Most recent by Yann Consolin-Oracle Supply Chain Planning and Collaboration -
How to setup Alternate UOM for Buy order release from Supply chain planning?Hi, As per the new release in 25D, we can release buy planned orders in alternate UOM. Please suggest How to setup Alternate UOM for buy release, if there is no availabl…Akshay Kumar1 61 views 8 comments 0 points Most recent by DipanjaliP Supply Chain Planning and Collaboration -
Supply planning Average Daily Demand Calculation for PAB and Projected On hand Days of coverSummary: My supply plan horizon is in day bucket, Horizon for Average Daily Demand is 60 days, i want to understand the calculation behind the Average Daily Demand as I'…Gaurav G S Nevrekar 13 views 1 comment 0 points Most recent by Sunil Jami-Oracle Supply Chain Planning and Collaboration -
Constrained SP: Pre-build not happening even when earlier buckets have available capacitySummary: I am testing constrained planning behavior with weekly buckets (Monday start), using a 5-day × 8-hour resource calendar (excluding Japanese holidays). Item FG r…Yuki Kobayashi-Oracle 24 views 5 comments 0 points Most recent by Sebastian Thomas Supply Chain Planning and Collaboration -
how to manually enter a forecast in fusion supply planSummary: Content (please ensure you mask any confidential information): Version (include the version you are using, if applicable): Code Snippet (add any code snippets t…felipe vieira 21 views 5 comments 0 points Most recent by Yann Consolin-Oracle Supply Chain Planning and Collaboration -
How to plan for two subinventories in Supply planningSummary: We have business requirement to plan in MRP plan two subinventories Content (please ensure you mask any confidential information): Business requirement: plan fo…Jsparks 15 views 4 comments 0 points Most recent by Yann Consolin-Oracle Supply Chain Planning and Collaboration -
Avoid supply planning of items planned by replenishment planWe have a requirement where, within the same organization, certain items need to be planned using a Replenishment Plan, while the remaining items should be planned using…Subhash Singh Tomar 15 views 2 comments 0 points Most recent by Subhash Singh Tomar Supply Chain Planning and Collaboration -
How to upload supply plan recommendations from fusion to oracle EBS?Summary: After running the supply plans in fusion and extracting the Make, Buy and transfers recommendations, how to upload them in Oracle EBS? We want to extract the re…zee123 6 views 1 comment 0 points Most recent by Yann Consolin-Oracle Supply Chain Planning and Collaboration -
Forecast consumption is not happening even after creating a Sales Order. What could be the reason?Summary: Why is forecast consumption not occurring even after creating a Sales Order in Supply Chain Planning? What could be the possible reasons or missing setups causi…Varun_Dave 14 views 2 comments 1 point Most recent by Varun_Dave Supply Chain Planning and Collaboration -
Updating planned OrdersSummary: Is there a way to update planned orders created by Supply Planning Cloud ?. We need to update the planned orders created by Supply Planning Cloud by changing th…Gajanan.. 23 views 2 comments 0 points Most recent by Alex D-Oracle Supply Chain Planning and Collaboration -
Layout rebuildSummary: Layout rebuild/migration from Legacy to Redwood Content (please ensure you mask any confidential information): Any automated way to migrate legacy UI's layouts …User_XSW9J 11 views 1 comment 0 points Most recent by Scott Malcolm-Oracle Supply Chain Planning and Collaboration -
How to find period start dates/end dates of a manufacturing calendar?Summary: How to find period start dates/end dates of a manufacturing calendar? Content (please ensure you mask any confidential information): Is there an easy way to fin…gouyang 31 views 5 comments 0 points Most recent by Sebastian Thomas Supply Chain Planning and Collaboration -
Can we explode Repair or Rework order in Supply PlanningSummary: Can we explode Repair or Rework order in Supply Planning Content (please ensure you mask any confidential information): Version (include the version you are usi…Akshaykumar Trivedi 25 views 4 comments 0 points Most recent by Sebastian Thomas Supply Chain Planning and Collaboration -
Calendars exceptions loaded to fusion not considering in planned order genarationSummary: We have loaded the calendar exceptions for some test calendar, and they are visible under the Review Calendars section in Fusion Supply Chain Planning. This cal…Sangeetha P 22 views 11 comments 0 points Most recent by Sangeetha P Supply Chain Planning and Collaboration -
Supply planning cloud integration with JD Edwards, existing oracle supported adaptersSummary: We have a requirement to integrate JD Edwards with Oracle Supply Planning Cloud. For Oracle EBS, Oracle provides a drop‑in patch to support this integration. Is…NareshT 21 views 3 comments 0 points Most recent by RakeshOracle-Oracle Supply Chain Planning and Collaboration -
archive time levelSummary: Hi Guru, we are about to enable archive for the supply plan, if i choose the archive time level at weekly, do i have to schedule build plan archive at weekly ba…JasonZZZL 12 views 6 comments 0 points Most recent by RakeshOracle-Oracle Supply Chain Planning and Collaboration -
Trying to create forecast not its not loading into staging tablesSummary: Hi Team, I am trying to create Forecast through FBDI process. After uploading i have ran Load Planning Data from Flat Files it was completed but Forecast was no…Sruthi Reddy 33 views 9 comments 2 points Most recent by Sruthi Reddy Supply Chain Planning and Collaboration -
How to use FG item forecast Only to Plan RM in Make-to-Order ScenarioWe have a planning requirement where Finished Goods (FG) are make-to-order, so they should be planned only when a Sales Order is created. However, we still want to use t…Prakash Muthukumar 22 views 2 comments 0 points Most recent by Yann Consolin-Oracle Supply Chain Planning and Collaboration