How do I change a supply plan 2 order quarterly instead of monthly?
We are in Canada and a lot of our product comes from the States and it gets quite expensive. I have been setting up and testing Demand Planning and it great, right up to where it creates the Purchase Order recommendations. I have tried changing time fences, and reschedule days with no success. It recommends a monthly quantity and what I want to do is order everything recommended for say the next 3 or 4 months. I have had to manually add up the months and enter it on the first line of the Order