Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
New AI Community Guidelines. Please review and follow them to ensure AI use stays safe, accurate, and compliant.
Keep an eye out for upcoming NetSuite events, including meetups, workshops, and webinars. These sessions are a great way to connect with peers, learn from experts, and stay current on the latest NetSuite updates and best practices. Registration links are provided in each event.
Save $30 - limited to first 1,000 registrants
Join the NetSuite community to innovate, connect, and discover what’s next.
SuiteWorld brings thousands of innovators, builders, and leaders together to learn, connect, and shape what’s next. This October, explore how to build a stronger foundation for growth through inspiring keynotes, major product reveals, hands-on sessions, and unforgettable moments—all in one place for our biggest event of the year. Register now
Join the NetSuite community to innovate, connect, and discover what’s next.
SuiteWorld brings thousands of innovators, builders, and leaders together to learn, connect, and shape what’s next. This October, explore how to build a stronger foundation for growth through inspiring keynotes, major product reveals, hands-on sessions, and unforgettable moments—all in one place for our biggest event of the year. Register now
Supply Planning Workbench not respecting operation-level start dates on Work Orders
We have Work Orders with multiple operations, each with its own start date and components assigned per operation. For example, WO #178 has a component (item 300207) assigned to Operation 600 (Wrap) with a start date of 7/2/2026. However, the Planning Workbench is showing that component as needed today (6/11/2026) instead of 7/2/2026.
We have verified:
- Operations have correct start dates in the WO
- Components are correctly assigned to each operation in the BOM/Routing
- All lead times in the item master are blank/zero
- Planning Repository has been refreshed multiple times
It appears the Supply Planning module is using the WO's overall start date (or today's date if the WO is past due) instead of the individual operation start dates for component requirements.